Astronergy CHSM72M-HC Installationshandbuch - Seite 2
Blättern Sie online oder laden Sie pdf Installationshandbuch für Kontrolleinheit Astronergy CHSM72M-HC herunter. Astronergy CHSM72M-HC 12 Seiten. Crystalline silicon pv
Auch für Astronergy CHSM72M-HC: Installationshandbuch (12 seiten), Installationshandbuch (12 seiten), Installationshandbuch (18 seiten), Installationshandbuch (19 seiten), Handbuch (19 seiten)

1. Introduction
1.1 Purpose
This document provides detailed instructions and valuable safety information regarding the
installation, electrical connection, and maintenance of following Chint Solar Crystalline Photovoltaic
modules:
CHSM60M(BL)-HC(166) CHSM60M-HC(166)
All the instructions should be read and understood before installation. The installers should
be trained and conform to all safety precautions in this guide when installing the module. Keep
this guide in a safe place for further reference.
1.2 Limitation of Liability
Because the use of this manual and the conditions or methods of installation, operation, use
and maintenance of photovoltaic (PV) products are beyond Chint Solar's control, Chint Solar
does not afford the responsibility and expressly disclaims liability for loss, damage, or expense
arising out of or in any way connected with such installation, operation, use or maintenance.
Chint Solar reserves the right to change the manual without prior notice.
1.3 Precautions of Installation
1.3.1 Module's unpack and transfer
a) When the whole pallet of modules are delivered to the site and unloaded, make sure the
safety of the modules especially if they need to be lifted for roof projects. Put them into a
protective device and then lift it to the roof in case of bumping against the wall during the
lifting process.
b) Firstly, tear the stretch film, then move away the top cover after cutting off each module
packing strip while unpacking. Two operators work as a group, grasp the module frame
tightly in the same direction and take out the module one by one. It is a must that the
operators remove the adhesive tape of the fixed module one by one, rive one piece and
then take out one piece of module. We don't allow to tear off all the adhesive tape at one
time in to prevent the whole package from toppling over or falling down. The whole process
must be taken very gently. Don't collide with any hard objects or let any parts of the frame
touch and drag on the ground.
c) After unpacking the modules should be installed that day as far as possible. It's
recommended to take the right amount of modules according to the progress of the project
Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
CHSM72M-HC(166)