3.3 Battery connection

For safe operation and compliance, a separate DC over-current protector or disconnect
device is required between the battery and the inverter. In some applications, switching
devices may not be required but over-current protectors are still required. Refer to the
typical amperage in the table below for the required fuse or circuit breaker size.
Model
Wire Size
5/6/7.6/8Kw
2AWG
Chart 3-2 Cable size
2
Cable(mm )
Torque value(max)
35
24.5Nm
- 07 -
All wiring must be performed by a professional person.
Connecting the battery with a suitable cable is important for safe and
efficient operation of the system. To reduce the risk of injury, refer to
Chart 3-2 for recommended cables.
Please follow below steps to implement battery connection:
1. Please choose a suitable battery cable with correct connector which can well fit into the
battery terminals. 2. Use a suitable screwdriver to unscrew the bolts and fit the battery
connectors in,then fasten the bolt by the screwdriver,make sure the bolts are tightened
with torque of 24.5 N.M.
2. Nm in clockwise direction,make sure polarity at both the battery and inverter is
correctly connected.
3. In case of children touch or insects go into the inverter,Please make sure the inverter
connector is fasten to waterproof position by twist it clockwise.
Installation must be performed with care.
Before making the final DC connection or closing DC breaker/disconnect,
be sure positive(+) must be connect to positive(+) and negative(-) must be
connected to negative(-). Reverse polarity connection on battery will damage
the inverter.