AlphaESS SMILE-G3-S5 Inbetriebnahme von Hardware - Seite 5

Blättern Sie online oder laden Sie pdf Inbetriebnahme von Hardware für Lagerung AlphaESS SMILE-G3-S5 herunter. AlphaESS SMILE-G3-S5 18 Seiten.

Commissioning Procedures
1.3.1.1 Basic Parameters Settings
Storage PV Capacity
Click "Submit" when the
settings are complete.
DC Mode
Three mode options: DC/AC/Hybrid
DC
Storage PV capacity: PV capacity on the energy storage inverter side
5 kW
On the grid side, if only a CT is installed, please select CT for grid side.
If the grid meter is installed, please select Meter for grid side. If this meter is a
CT meter and the CT ratio is not 1, please select CT below and input the Meter
CT Ratio. If this meter is not a CT meter or the CT ratio is 1, please do not select
CT below.
Note:
When the safety standard is set as AS4777.2 (Australia and New Zealand), the
secondary sub-options can be selected according to the region or local grid
company.
You can set the allowable feed-in ratio from 0%-100%.
5