INSTALLATION
The controller is desi g ned for wall mounting in a control room or working area. The enclosure incorporates a sub
panel assembly and window.
1. CONTROLLER INSTALLATION/MOUNTING
Securely mount the controller to the wall using four (4) mounting screws with lock washers and nuts. Make
sure there is room for the door to open.
2. INTERCONNECT WIRING
Interconnect wiri n g is identified in the customer wiring diagram drawings in this manual. It is recommended that
all wiri n g is shielded and common shielding practices be used for installation to reduce the possibility of radi o
frequency interference.
Step 1: Connect sensor to the interconnect cabl e . Record wire colours and what terminals they are connected
to. See sensor information as to number of wires used and their connection.
Step 2: Terminate the other end of the interconnect cable from sensors at the connectors located insi d e the
controller on the upper right of the motherboard. Observe correct polarity between sensor and
controller connections. Failure to do so may result in damage to ampl i fier circuits.
Interconnecting wiri n g between controller and sensors
3. ALARM RELAY OUTPUTS
Step 1: Terminate wiring to alarm output connectors as identified in customer wiri n g diagram drawing.
Step 2: Terminate power supply input wiri n g as identified in customer wiring diagram.
4. PREPARATION FOR OPERATION
Step 1: Check all wiring for correct polarity and good terminal connections.
Step 2: Appl y power and observe visual indi c ators.
- Input Module indi c ator lights may cycle between off, green, red and yell o w upon start up.
sensors will require a stabilization period. Consult specificati o n for the particular sensor
Step 3: Check voltage reading at each sensor.
This measurement will depend upon main power supply setting.
- +12 VDC to 14 VDC between (+) and (-) terminal connections.
5. INSTRUMENT START-UP
Step 1: Let the sensor settle after power has been appl i ed. See sensor data for settling time.
Step 2: A zero air sample should be applied to each sensor to check absolute zero when a continuous gas
background exists in the area where the sensor is installed.
NOTE: Airtest gas monitors are shipped cali b rated and should not require any adjustment provided voltage
reading and operational tests give correct indi c ation. However, it is recommended that a cali b ration
test be performed after installation.
Step 3: Testing of response to the presence of gas using a test sample or cali b ration sample of gas should be
appl i ed to each sensor.
Distributed By:
(800) 821-4863 TOLL FREE
GLOBAL CONTROLS, INC.
3008-B 16TH AVE W.
(206) 282-4666 TEL
SEATTLE, WA 98119
(206) 282-4888 FAX
3