9. Attach the outer rail section to the sides of
the rack using the supplied M5 screws and
cage nuts (see figure 4). Use two screws
at the back and two screws at the front of
each rail (eight in total).
10. With another person, lift the server up to
the rack and slide the two rail sections
together on each side.
11. Secure the server in the rack with the rack
ears using two M5 screws for each rack
ear.
Note: Do not support the Acano Server
on the rack ears alone.
12. Unpack the box containing the two power supplies. They are identical.
13. Move to the back of the rack and slide the power supplies fully into the Power A and B slots
in the back of the server until they latch (see Figure 2).
Notes:
Do not connect power to the server at this time.
DC power option only: See
power at this time.
14. Connect a network cable to the Admin interface and to your administrator network.
This interface is used to set up time servers and to upgrade the software version. (Both are
outside the scope of this Installation Guide.) Connections to the Admin interface are via SSH
or SFTP.
15. Connect a network cable to the A interface and to your production or testing network.
This media interface is also used for access to the Web Admin Interface and therefore for
server configuration. An HTTPS connection is required – attempting to connect using HTTP
will fail. A certificate is required – as explained in later sections.
Note: Interfaces A to D will operate at the speed of the network switch that they are
connected to. If you are using a speed of 10G be sure to use the appropriate cable for the
Acano solution: Installation Guide 76-1002-04-D

Figure 4: Cage nut locations for the rack rails

Appendix A
for DC wiring instructions. Do not switch on the
Hardware Installation