ABB ENTELLIGUARD G Manual - Halaman 15

Jelajahi secara online atau unduh pdf Manual untuk Peralatan Industri ABB ENTELLIGUARD G. ABB ENTELLIGUARD G 17 halaman. Procedure for quality checks of dr iec

2. CHECK THE TERMINALS ALIGNMENT AS PER DRAWING / INSTRUCTION SHEET.
Before rack-in check whether all the terminals mounted on the breaker are aligned properly as instructed in the
. d rawing or the instruction sheet.
.
3. RACK-IN HANDLE NOT INSERTED BEFORE AND DURING LOADING THE BREAKER.
.
Must ensure that the racking handle is not inserted before and during loading the breaker. Handle should only be
.
inserted when the breaker is pushed inside the cassette to dead end condition.
4. GREASE APPLICATION.
.
Visual check of grease application on cluster fingers of moving portion.
Rev. A
CHECKS BEFORE LOADING THE BREAKER
PROCEDURE FOR QUALITY CHECKS OF
DR IEC ENTELLIGUARD G FAMILY
Doc.N°
1SDH00XXXXX
Page N°
15/17