Installation and Commissioning Guide

05.06. Return Air Filter

Air filters must be provided in the return air side of the unit to maintain the efficiency and prolong the operation of the unit.
These are also paramount to satisfy the requirement for a clean and hygienic room condition. Air filters must be placed in an
easily accessible location for service and maintenance.
IMPORTANT NOTES TO INSTALLER
• Air filters are not supplied with the unit as individual air filtration requirements vary.
• Ensure that filters are cleaned / replaced regularly.

05.07. Field Pipe Connection

Specifications and installation requirements for field pipe connections are contained in the Installation and Commissioning
Guide of the outdoor unit that matches your indoor unit. Please refer to this guide and thoroughly understand the procedures
for safe and correct indoor and outdoor connection. ActronAir highly recommend all field pipes to be insulated.

05.08. Electrical Field Connection

The power supply and control communication data to the indoor unit are supplied via the outdoor unit. Please refer to the
wiring diagram supplied with the outdoor unit for specifications.
All electrical work must be performed by a licensed electrician and must conform with the wiring diagram and all relevant
electrical authorities.
10
Installation & Commissioning Guide - ESP Platinum QUE Split Ducted Units
Doc. No.0525-061 Ver. 1 190131
ESP Platinum QUE - Three Phase