• Make the hydraulic connections as instructed on the nameplate on the frame or on
the plate arrangement drawing.
• Never insert foreign matter into the circuit.
• No strain should be placed on the pipes (weight of connected pipes, expansion,
vibrations etc.).
• If threaded couplings are used, do not apply the tightening torque to the threaded
nozzles.
• Threaded nozzles are not welded to the fixed head. To avoid damaging the first
gasket, hold the threaded nozzles in place with pliers and screw on the pipes (Fig. 4).
• If the ports on the fixed head are fitted with protective
built-in linings, the linings must be sufficiently compressed
so that the head and the counter-flange are separated by
a 2 mm gap (tightening any further will damage
the linings).
• In the case of a multi-pass heat exchanger (fluid inlet and
outlet ports on both ends): install an expansion fitting or a
horseshoe loop and use detachable pipes so that more plates
can be added and the movable follower can be removed.
Fig.4
3.4 - Insulation and protection accessories
3.4 - Insulation and protection accessories
If necessary (e.g. residual risk of hot surface), affix the appropriate visual warning signs also on the external surface of the insula-
tion or of the protection accessory.
TF insulation
PB insulation
36
ATLANTIC BOILERS, PO BOX 11, ASHTON UNDER LYNE, OL6 7TR T: 0161 621 5960 E: [email protected] www.atlanticboilers.com
• Check the tightening dimension specified on the nameplate.
Refer to section 5.7 if retightening is needed.
• Make the hydraulic connections as instructed on the name-
plate on the frame or on the plate arrangement drawing.
• Never insert foreign matter into the circuit.
• No strain should be placed on the pipes (weight of connect-
ed pipes, expansion, vibrations etc.).
• If threaded couplings are used, do not apply the tightening
torque to the threaded nozzles.
• Threaded nozzles are not weld-
ed to the fixed head. To avoid
damaging the first gasket, hold
the threaded nozzles in place
with pliers and screw on the
pipes (Fig. 4).
• If the ports on the fixed head
are fitted with protective built-in
linings, the linings must be suf-
ficiently compressed so that the
head and the counter-flange are
separated by a 2 mm gap (tightening any further will dam-
age the linings).
• In the case of a multi-pass heat exchanger (fluid inlet and
outlet ports on both ends): install an expansion fitting or a
horseshoe loop and use detachable pipes so that more plates
can be added and the movable follower can be removed.
Plate pack protection
Drip tray
Fig.4