4.Adjustment for Pre-load
(1) Spring pre-load can be adjusted to rotate Stem.
When rotating, keep pulling Stem to Collet side
(Figure 4);
Rotating to "+" direction (clockwise) = pre-load increase
Rotating to "-" direction (counter-clockwise) = pre-load decrease
(2) After adjusting pre-load, please check if Stem is
locked and cannot be rotated.
※ For the min. pre-load, rotate Stem to " - "
direction as much as possible and then rotate
it "+" side and the point where is locked first
time, is the min. pre-load.
※ The relationship between the number of Stem
rotation and Spring pre-load is as below chart
(approx.).
Figure 4
Stem
ステム
Pre-load decreases
when rotating to
- direction
Collet
コレット
The number of
Stem rotation
0(Min.)
1
2
3
4(Max.)
5.Replacement of Spring
When exchanging Spring depending on workpiece
material and burr, please follow below procedure to
replace it. Spring for exchange is option.
(1) Following the procedure of 「4.Adjustment for
Pre-load」, set pre-load the maximum value and
then detach Guide Shaft from Shank. (Figure 5)
Detach
Pre-load the max. value. If loosening
Guide Shaft by force, it may cause the
Caution
tool broken.
Figure 5
Guide Shaft
Pre-load increases
when rotating to +
direction
Pre-load [g]
Spring (Standard)
120
320
520
720
920
Guide
Shaft
after
Shank
(2) Detach C-shape Stop Ring inside Stem. For
detaching, please use the tool for C-shape Stop
Ring (for Hole, size: No.1)
(3) After loosening Spring Receiver inside Stem,
Spring can be taken off. When detaching Spring
Receiver, please pay attention not to lose Steel Ball
2pieces. (Figure 6)
Figure 6
Caution
(4) After Spring is replaced, attach Steel Ball and
Spring Receiver to Stem, and then put C-shape
Stop Ring. The recessed side of Spring Receiver is
toward Spring.
(5) Using Guide Shaft, contact Spring Receiver to
C-shape Stop Ring, and then assemble Guide
Shaft to Shank. (Figure 7)
Caution
6.Maintenance
(1) When this holder is maintenance, please follow 「5.
Replacement of Spring」 and disassemble (Figure
5~7).
setting
(2) After Stem is cleaned, add Spindle oil (VG10 or
less), etc. to sliding surface. (The oil should be
low-viscosity.) Then, assemble the tool.
Caution
Remarks
This tool cannot be guaranteed for all process. Depending on the
situation, change the processing parameter and adjust it. We cannot
take any responsibility for any loss or consequential damage incurred
by using this product.
C-shape
Spring
Stem
Stop Ring
Spring Receiver
Steel Ball (2pcs)
Steel Ball 2 pieces are assembled to
Spring Receiver. Please be careful not to
lose then when it's dismantled.
Contact C-shape Stop Ring
Figure 7
and Spring Receiver
Before assembling Guide Shaft, Spring
Receiver has to be contacted to C-shape
Stop Ring. If assembling Guide Shaft by
force, it may cause the tool broken.
If this holder is not used long time, the
sliding surface may be stuck and the
floating structure does not work properly.
After long term of no use, please
maintenance the tool at first, and then
use it.