Installation Data
160304PSL/R, 160304PSML/R,
260304PSL/R, 260304PSML/R
Fax on Demand # 9034
Installation Instructions
12 12
13 13
Measure the distance between the top of the back horizontal flange and the bottom of the pan
Fasten a 1" x 3" (25mm x 75mm) ledger strip along rear of alcove and
ledge, approximately 1-1/2" (40mm). Mark this dimension on the back studs (or wall), below
along both sides (immidiately below the lower marks made on framing).
the first mark.
14 14
15 15
Install drain assembly per manufacturer's instructions. (Optional) Mix foundation material. Place three or four
Place base into framing pocket.
mounds on the subfloor around but away from drain hole. The mounds should be placed high enough so that when
the unit is set, it will cause the plaster to displace and spread.
16 16
17 17
Tap down until level. Level lengthwise and widthwise using 3 ft. (915mm)
Pre-drill horizontal flanges along top of base section and fasten into each corresponding stud.
level by shimming or depressing foundation materials.
Pre-drill both (vertical) side flanges and fasten to side studs 8" (200mm) on center.
The unit must be set level. Apron should be firmly on the floor.
Place cardboard to protect finish.