Cisco UCS B250 M1 Installation And Service Note - Page 22

Browse online or download pdf Installation And Service Note for Server Cisco UCS B250 M1. Cisco UCS B250 M1 34 pages. Extended memory blade server

Cisco UCS B250 M1 Installation And Service Note
Working Inside the Extended Memory Blade Server
S e n d d o c u m e n t c o m m e n t s t o u c s - d o c f e e d b a c k @ c i s c o . c o m
Figure 11
Close the socket latch. See
Step 2
Lock the socket latch into place with the hook. See
Step 3
Using the tube of thermal compound provided with replacement CPUs and servers (Dow-Corning
Step 4
TC-1996, Intel D54816-0 or an equivalent may also be used), add a protective film of thermal compound
to the bottom of the heat sink where it will contact the CPU. If the heat sink shipped with a thermal pad,
remove the protective film and verify that the CPU is clean and will bond successfully with the heat sink.
Replace the heat sink. See
Step 5
Caution
Make sure that the heat sink fins are aligned to run along the length of the blade server (see
Step 6
Secure the heat sink to the motherboard by tightening the four captive screws in an X pattern. See
Figure
Installing Memory
Always install Cisco-supplied DIMMs according to the population rules in
Note
guidelines in
Check the server's service profile setting in UCS Manager before adding memory to make sure that the
new memory will be recognized. The service profile may not be set up for the added memory.
To install a DIMM into the extended memory blade server, follow these steps:
Step 1
Open both DIMM connector latches, refer to callout 1 in
Cisco UCS B250 Extended Memory Blade Server Installation and Service Note
22
Inserting the CPU and Replacing the Heat Sink
Figure
Figure
11, callout 6.
Supported
DIMMs.
11, callout 2.
Figure
11, callout 3.
11, callout 5.
Figure
Table
7, and follow the
12.
Figure
11).
OL-22474-03