Installing the Cisco ASR 920 Series Router
SUMMARY STEPS
1. Attach the AC power retainer chord as shown in the figure below.
2. Lift the power retainer and plug in the AC power supply.
DETAILED STEPS
Step 1
Attach the AC power retainer chord as shown in the figure below.
Figure 12: Attaching the AC Power Retainer Chord
Step 2
Lift the power retainer and plug in the AC power supply.
Cisco ASR 920 Series Aggregation Services Router Hardware Installation Guide
Install the AC Power Cables
15