Stage 3: On-Site Installation Procedure

Please review the Scope of Works document completed during the pre
sales process.
As part of the pre-sales process a site inspection by the level 4 hardware
colour specialist is required. The site inspection will involve completing a
site survey document called the Scope of Works.
The production sales specialist is responsible for providing this document
to the technician. The site survey will confirm all the necessary
requirements for installing a Pro C900 / Pro C900s model at the
customers' site.
It is recommended to allow two to three days (depending on the
configuration) for one technician to complete the on-site installation
procedure. This should allow sufficient time to confirm the machine's
performance prior to handing the machine over to the print solutions
consultant (PSC).
Please follow the on-site installation procedure in the order that is listed
below;
1. Arrive prior to machine delivery and ensure the site is ready for
2. If flooring is required, arrange for the floor boards to be delivered
3. Locate the mainframe into position. If flooring is required the
4. Install the fusing unit.
5. Levelling the mainframe: This is a critical step. Ensure that the
6. Fill the oil tank with silicon oil.
7. Oil Pump Connector: Measure the 32 amp wall socket. If the input
8. Install the LCT-MF (large capacity tray) (Pro C900s only) and all
9. Install all of the remaining A4 non-coated paper and 100gsm A3
10. Install all peripherals as performed in the run-up procedure.
11. Install hardware components for MFP options such as File Format
12. Connect an Ethernet cable to the GW port for @Remote.
Colour High Volume Production System - Installation Guide
Pro C900
delivery.
prior to the delivery of the machine. This will allow time for the
floor boards to be correctly levelled and placed in the right
position.
transport company will require a sheet of aluminium (or something
similar) to push the mainframe and options up on to the 19mm
Yellow Tongue floor boards.
following guidelines are followed.
a. Front to rear: Must be within ± 2.5mm/1000mm
b. Right to left: Must be within ± 2.5mm/1000mm
voltage is 235 volts or above connect the oil supply connector to
CN617. If the input voltage is below 235 volts, connect the oil
supply connector to CN616. The default position for the oil supply
connector is CN616.
paper feed options.
paper into all trays.
Converter (FFC), Data Overwrite Security (DOS) and the VM Card.
Note: After connecting the Ethernet cable and entering the
@Remote IPv4 port details (see p. 16 System Settings: