ACQ580-01 drives
Quick installation and start-up guide
This guide is applicable to the global product types. There is a separate guide for the North American product types.
Documentation in other languages
Safety instructions
WARNING! Obey these instructions. If you ignore them, injury or death, or damage to the equipment can occur. If
you are not a qualified electrical professional, do not do electrical installation or maintenance work.
•
Do not do work on the drive, motor cable, motor, or control cables when the drive is connected to the input power.
Before you start the work, isolate the drive from all dangerous voltage sources and make sure that it is safe to start the
work. Always wait for 5 minutes after disconnecting the input power to let the intermediate circuit capacitors
discharge.
•
Do not do work on the drive when a rotating permanent magnet motor is connected to it. A rotating permanent
magnet motor energizes the drive, including its input and output terminals.
•
Frames R1...R2, IP21
(UL Type 1): Do not lift the
drive by holding it from the
cover. The cover can come
loose and cause the drive to
fall.
•
Frames R5...R9: Do not tilt the
drive. The drive is heavy and
has a high center of gravity. It
can topple accidentally.
•
Frames R5...R9: Lift the drive
with a lifting device. Use the
lifting eyes of the drive.
1. Unpack the delivery
Keep the drive in its package until you are ready to install it. After unpacking, protect the drive from dust, debris and
moisture. Make sure that these items are included:
•
cable box (frames R1...R2 and R5...R9, IP21 [UL Type 1])
•
drive
•
mounting template
•
control panel
•
quick installation and start-up guide
•
multilingual residual voltage warning stickers
•
hardware and firmware manuals, if ordered
•
options in separate packages, if ordered.
Make sure that there are no signs of damage to the items.
2. Reform the capacitors
If the drive has not been powered up for a year or more, you must reform the DC link capacitors. Refer to
reforming instructions (3BFE64059629 [English])
Ecodesign information
(EU 2019/1781 and SI 2021 No. 745)
R1...R2
R5...R9
or contact ABB technical support.