Note:
For sheds with the Raised Floor Modification option the studs will be 1.780m long to allow the Wall Sheets to pro-
trude 20mm below the Bottom Plate. Refer to Raised Floor Modification section (Page 15).
Note:
If fitting a window in the Back Wall, there will be no centre stud on that side. Instead nail in a full length Nog (3.290) using
Window Studs (.883) to get correct height. Position one Window Stud centrally beneath the Nog and nail in place. Further
window studs and Nogs are fitted after the cladding is on.
Step 1: End Walls: Select one 1.210m End Base Plate
(Green), one 1.210m End Top Plate (Red) and two
Studs (Yellow). Lay out Plates and two Studs on a flat
surface and nail together using two 75mm nails per
join. Position 1.120m Nog .883m down from Top Plate
and nail in place. Repeat with other end wall.
Step 2: Select one 3.380m Base Plate (Green) one 3.380m
Top Plate (Red). Stand up End frame with the Stud
side of the frame on the ground. Nail 3.380m plates to
frame using two nails per join. Ensure Red joins to Red
and Green joins to Green. Repeat with other end
frame. Nail in back wall centre stud using 1.622m Nogs
to get correct position. Position Nogs .883m down from
Top Plate and nail in place.
Step 3: Select one 3.380m Base Plate (Green) and the Ridge
Beam (90 x 45). Nail in place. Ensure Red joins to Red.
Step 4: Carefully roll the frame over so that the Ridge Beam
and Base Plate (Green) are on the ground. Select two
studs (Yellow) and one .785m Nog and one 1.622m
Nog. Nail in Studs using the nogs to get the correct
position top and bottom. Position nogs .883m down
from the Top Plate and nail in place.
Step 5: Carefully roll frame over onto its base. If fitting a Kiwi
Floor, fit Floor Joists now. Place the joist centrally and
nail in place using three 75mm nails per end.