HI-FOG 1900 Identifizierungs- und Berichtigungsverfahren - Seite 12

Blättern Sie online oder laden Sie pdf Identifizierungs- und Berichtigungsverfahren für Irrigation System HI-FOG 1900 herunter. HI-FOG 1900 18 Seiten. A1000 type assembly body with stop valve

18/09/2017
c. Check that the system stabilizes to stand-by pressure (25 bars if not
otherwise indicated). (Person A)
d. Check that there are no leaks from the installed sprinklers. (Person B and C)
e. Remove the plug from the flushing valve and connect the flushing hose to
the flushing valve. Make sure that you can hold the flushing hose firmly with
both hands during the system flushing and point it to a place where water
can be safely sprayed. (Person B and C)
NOTE: The water exits the hose with high pressure. Be sure that you can
hold the hose firmly with both hands!
f. Open the flushing valve to create flow in the system. (Person C)
g. The pump unit should activate within 1 minute.
h. Check from the control / mimic panel or the ship automation system that the
pump unit starts and verify that the correct section gives the correct alarm.
Reset the audio alarm from the buzzer reset/acknowledge button. (Person
A)
i. Let water flow from the hose for a couple of minutes to flush the section.
(Person B and C)
j. Close the flushing valve. (Person C)
k. Reset the system from the control panel after the flushing valve has been
closed and the system has reached 130 bars pressure. (Person A)
l. Check that the system stabilizes to stand-by pressure (25 bars if not
otherwise indicated). (Person A)
m. Disconnect the flushing hose from the flushing valve and install the plug
back into place. (Person C)
After competing these steps proceed to the next section in the work plan.
4.4. Post Actions
After finalizing the corrective actions in all sections, the system should be put
back into normal standby mode and the nitrogen accumulator unit should be
switched back on / reconnected. (see
NOTE: Make sure that there is no activation demand on for the HI-FOG
system before reconnecting the nitrogen accumulator units!
-
Inform the bridge and ECR that the work is completed and the system is
in normal stand-by mode.
Send the filled Follow-Up form to Marioff [email protected]
Document number 0003301084
Figure 06
Ver. A
Figure 07
and
).
Page 12 of 18