Dell S3100 Series Handbuch
Four-Post Threaded Configuration
To install the Dell ReadyRails system using the four-post threaded
configuration, follow these steps.
1.
Remove the flange ear castings from each end of the ReadyRails
assemblies. Use a Torx driver to remove the two screws from each flange
ear and remove each casting. See item 1 of the following figure. Retain
the castings for future rack requirements.
2.
For each rail, attach the front and rear flanges to the post flanges with
two user-supplied screws at each end. See item 2 of the following figure.
Figure 4. Four-Post Threaded Configuration
10
Installation