PART B: UNIvERsAL PEELINg TOOLs
By using the aquatherm universal peeling tools the end pieces of the
aquatherm OT (oxygen tight), UV (UV-resistant) and MS (multilayer stabi)
pipes can be peeled. By the uniform removal of the outer layer of the
pipe any extension of the pipe system by electrofusion socket or fitting
is possible. The universal peeling tools are available in the sizes Ø 20-
Ø 125 mm (Art.-No. 50479 – 50488). The peeling process is done either
mechanically or manually. For the mechanical processing two attachment
plates for pipe sizes Ø20- Ø63 mm (Art.-No. 50499) and Ø75- Ø125 (Art.-
No. 50500) mm are available. For the mechanically processing of the
electrofusion sockets the peeler is extended by an attachment (Art.-No.
50489 – 50498). The power drill should have a high torque.
1. INsTRUCTIONs fOR ThE MEChANICAL PEELINg PROCEss
1.1. The attachment plate is clamped with the hexagon bolt in the power
drill.
1.2. The peeler is fixed with its screws in the slot matching the diameter
of the attachment plate and rotated clockwise so that the peeler adheres
to the attachment plate.
1.3. The peeling tool clamped on the chuck is set by the lead to the end
of the pipe.
1.4. The peeling process starts with rotation of the peeling tool upon slight
force in axial direction. The peeling operation is completed when the
attachment plate strikes against the pipe end.
1.5. The pipe now can be welded by socket welding method.
2. INsTRUCTIONs fOR ThE MEChANICAL PEELINg PROCEss fOR
ELECTROfUsION sOCkETs
2.1. The extension is centered with the peeler through the superimposed
chamfer fit and fastened with three Allen screws.
2.2. The attachment plate is clamped with the hexagon bolt in the power
drill and connected with the peeling tool (see photo 1.2.).
2.3. The peeling process starts with rotation of the peeling tool upon slight
force in axial direction. The peeling operation is completed when the
carrier plate strikes against the pipe end.
2.4. The peeling tool is withdrawn from the pipe and the E-socket welding
process can start.
3. PEELINg INsTRUCTIONs fOR MANUAL PEELINg
3.1. For the manual peeling two handles are mounted at the peeling tool.
3.2. The peeling tool is pushed onto the untreated pipe up to the stop.
3.3. The peeling tool is turned clockwise as long as the marked peeling
depth (see table) is reached.
3.4. If the specified/marked peeling depth (see table) is reached, the peel-
ing tool is removed and the socket welding process can start. If the electric
socket can be used as a sliding sleeve, the peeling depth for the electric
socket welding (see table) must be doubled.