Check the running status of the system in "Step 3".
If the operation is normal as described in "Step3", please remember to deactivate
the "Charging/Discharging Setting" by clicking "OFF" and save the changes.
100
Commissioning Procedures
Step2
Select "ON" to Charge Batteries from Grid"
please set the "Charging period 1" for the time and the
SOC would be 100 under this operation.
Step3
The relative value should be like this:Load = PV
Battery
Battery should be in
charging
the picture
shows.±:
>>absorbing from grid: +;
to grid:-
If not correct, please check the CT or meter installed
direction of both grid and PV side
±
GRID –
status.PV arrow
should be as
<<