Cisco ONS 15454 Auspacken und Installieren - Seite 5
Blättern Sie online oder laden Sie pdf Auspacken und Installieren für Server Cisco ONS 15454 herunter. Cisco ONS 15454 40 Seiten. Four-shelf and zero-shelf bay assembly
Auch für Cisco ONS 15454: Installationsanleitung Handbuch (22 seiten), Install (32 seiten), Install (32 seiten), Auspacken und Installieren (42 seiten)
Recommended Material
Because most of the installation is complete when you receive the system, the bay assembly requires
little installation material. The most significant tasks are removing the packaging from the bay assembly
and removing the bay assembly from the shipping pallet. Because the actual installation of the bay
assembly in each facility is done according to local site practice, your material needs may vary.
Cisco recommends that you have the following items on hand for installation:
•
•
•
•
•
•
•
Unpacking Instructions
The ONS 15454 four-shelf and zero-self bay assembly ships in a corrugated container that covers the
rack on its shipping pallet. After removing the corrugated container, you must remove the bolts that hold
the rack to the pallet before moving the unit to the desired location.
assembly on a shipping pallet.
Cisco recommends that a minimum of three people move the bay assembly.
Caution
Use a forklift or pallet jack to place the shipping container as close to the installation location as
Step 1
possible.
Cut the plastic banding off of the cardboard shipping container.
Step 2
Remove the cap from the corrugated container.
Step 3
Pull the side panels away from the shipping pallet and set it aside.
Step 4
Remove the base plate from the bottom front of the rack:
Step 5
a.
b.
Step 6
Remove the four bolts that hold the rack to the pallet (rack base bolts).
Remove the vertical extenders if necessary.
Step 7
78-15720-04
A forklift or pallet jack to move the packaged bay assembly to the unpacking/staging area
A pair of scissors to cut the plastic banding on the shipping container
Utility blankets or their equivalent to protect the bay assembly while on the forklift or pallet jack
Phillips screw driver or cordless drill with Phillips bit
3/4 inch socket or box-end wrench for the earthquake floor bolts
Four optional kits listed in
Use this guide in conjunction with Cisco ONS 15454 documentation (procedure guide,
troubleshooting guide and reference manual), and the latest release of the
Cisco ONS 15454-FAP-LVD Operations Guide.
Remove the two screws that fasten the base plate to the rack.
Pull the base plate away.
Unpacking and Installing the Cisco ONS 15454 Four-Shelf and Zero-Shelf Bay Assembly
Table 3 on page 33
that can be ordered separately
Recommended Material
Figure 3
shows the four-shelf bay
5