Ariston microSYSTEM 21 RFFI Installationsanleitung Handbuch - Seite 22

Blättern Sie online oder laden Sie pdf Installationsanleitung Handbuch für Boiler Ariston microSYSTEM 21 RFFI herunter. Ariston microSYSTEM 21 RFFI 48 Seiten. Microsystem
Auch für Ariston microSYSTEM 21 RFFI: Benutzerhandbuch (16 seiten), Installationsanleitung Handbuch (24 seiten)

Ariston microSYSTEM 21 RFFI Installationsanleitung Handbuch
6.

MAINTENANCE

It is recommended that the following inspections be carried out on the
boiler at least once a year:
1 - Check the seals for the water connections; replace any faulty seals.
2 - Check the gas seals; replace any faulty gas seals.
3 - Visual check of the entire unit.
4 - Visual check of the combustion process or analysis of combustion by-
products (see section 4.5) and cleaning of the burner if needed.
5 - If called for by point. 3, dismantling and cleaning of the combustion
chamber.
6 - If called for by point. 4, dismantling and cleaning of the burner jets.
7 - Visual check of the primary heat exchanger:
-
check for overheating in the blade assembly;
-
clean the exhaust fan if needed.
8 - Adjustment of the flow rate of the gas: flow rate for lighting, partial load
and full load.
9 - Check of the heating safety systems:
-
safety device for maximum temperature (overheat thermostat);
-
safety device for maximum pressure (safety valve).
10- Check of the gas safety systems:
-
safety device for lack of gas or flame ionisation (detection
electrode);
-
safety device for gas cock.
11- Check of the electrical connection (make sure it complies with the
instructions in the manual).
12- General check of the combustion by-products of the
discharge/ventilation system.
13- Check of the general performance of the unit.
22