CUTLER-HAMMER 24kV Type W-VAC Circuit Breaker
4-8 ELECTRICAL OPERATION CHECK
After having completed all previous checks and
tests, the circuit breaker is ready to be operated
electrically. It is preferred that this check be
made with the circuit breaker in a TEST position
or by using a test cable, if the circuit breaker is
outside the cell structure.
CAUTION
!
BEFORE INSERTING THE CIRCUIT
BREAKER EXAMINE THE INSIDE OF THE
CELL STRUCTURE FOR EXCESSIVE DIRT
OR ANYTHING THAT MIGHT INTERFERE
WITH THE CIRCUIT BREAKER MOVEMENT.
!
WARNING
EXTREME CAUTION MUST BE EXERCISED
TO INSURE THAT PRIMARY CIRCUITS ARE
NOT ENERGIZED WHILE CHECKS ARE
PERFORMED IN THE CIRCUIT BREAKER
COMPARTMENT. FAILURE TO DO SO MAY
RESULT IN PERSONAL INJURY OR DEATH.
The circuit breaker is normally tested electrically
in its cell structure in the TEST position. To
achieve the TEST position, the circuit breaker
must first be placed in the cell structure and the
secondary contacts engaged. To complete this
testing procedure, the operator should first be
familiar with inserting and removing the circuit
breaker into and from the cell structure.
4-8.1
CIRCUIT BREAKER INSERTION AND
REMOVAL
NOTICE
Make certain that the levering nut is all of
the way forward in the TEST position before
attempting to insert a circuit breaker into its
compartment (FIG 4-2).
The extension rails must first be put into
position. Carefully engage the left and right
extension rails to the fixed structure rails and
ensure they are properly seated in place (Figure
4-3). Once the extension rails are properly in
place, the circuit breaker can be carefully
loaded on the extension rails using an overhead
Effective 12/98
lifter and lifting yoke. Remove the lifting yoke
when the circuit breaker is securely seated on
the extension rails.
Push the circuit breaker into the compartment
(the handles MUST be used to prevent the
breaker from tipping) until the TEST position is
reached as confirmed by the metallic sound of
the breaker levering latch engaging the levering
nut (Figures 4-2 and 4-4). Once the circuit
breaker is in the TEST position, the extension
rails can be removed.
To engage the circuit breaker secondary
contacts, raise the handle to the secondary
disconnect cage and pull the cage forward as
far as possible (Figure 4-5). As soon as control
power is available, the motor will start charging
the closing springs.
!
DO NOT USE ANY TOOL OTHER THAN THE
LEVERING CRANK (Figure 3-1) PROVIDED
TO LEVER THE CIRCUIT BREAKER FROM
TEST OR CONNECTED POSITIONS.
CORRECT OPERATION OF SOME OF THE
INTERLOCKS IS DEPENDENT ON THE USE
OF THE PROVIDED LEVERING CRANK.
PERSONAL INJURY OR EQUIPMENT
DAMAGE COULD RESULT FROM THE USE
OF A TOOL OTHER THAN THE PROPER
LEVERING CRANK.
The circuit breaker and integral levering
mechanism includes all necessary
interlocks that when interfaced with a
compatible Type W-VAC enclosure will
render the circuit breaker mechanism
mechanically and electrically trip-free during
the levering process. For information
pertaining to individual interlocks, refer to
paragraph 4-9 in this section.
To move the circuit breaker to the
CONNECTED position, engage the levering
crank with the structure mounted levering shaft
(Figure 4-6). Turn the levering crank in the
clockwise direction and the circuit breaker will
move slowly into the enclosure. When the
circuit breaker reaches the CONNECTED
position, it will become impossible to continue
turning the levering crank. Secondary contacts
Page 14 of 47
I.B. 8801C71H01
WARNING