▪ Apply teflon sealing tape (0.1x12 mm) to the changeover valve by 5 to 6 turns clockwise (Figure 4).
▪ Mount the changeover valve onto the liquid receiver; torque to 50 Nm (Figure 5).
▪ Apply teflon sealing tape (0.1x12 mm) to both NPT PRV's by 5 to 6 turns clockwise (Figure 6).
Figure 4
Figure 5
Figure 6
▪ Mount both PRV's into the changeover valve; torque to 40 Nm (Figure 7).
▪ Turn the spindle into middle position so that both PRV ports are open (Figure 8).
▪ Close the shut-off valves on the compressor (discharge port) and on the liquid receiver (Figure 9).
▪ Open the high-pressure valve and perform a bubble leak test on all connections between liquid receiver,
changeover valve and PRV's (Figure 10).
▪ Pressurize the liquid receiver with nitrogen (5 bar) and perform a preliminary leak test.
▪ Perform the final leak test at 80 bar.