Location requirements
General:
·
All of the location requirements for the charging station in the " Installation man-
ual" must be adhered to!
·
When mounting the floor-mounted columns in parking spaces or parking garages, appro-
priate anti-collision protection must be provided by the customer.
Concrete foundation:
·
The calculation, design and manufacture of the concrete founcation lies in the scope of
responsibility of the producer of the site.
·
A horizontal, level and sound foundation is required for installation.
To ensure safe and permanent anchoring, we recommend creating a concrete founda-
tion:
65cm (L) x 50cm (W), depth = min. frost limit but > 40cm, frost-free.
Concrete: C30/37 LP for XC4, XD1, XF4 or C25/30 LP for XC4, XD1, XF2
reinforced concrete: BSt 500 S; BSt 500 M
·
The base must permit the running off of any water that has entered the base.
·
All cables must be laid precisely in the centre of the concrete foundation from the base
and must have an excess length of approx. 1.5 m for the remaining installation activities.
·
During the production of the concrete foundation, the cables must be protected against
damage using appropriate measures (e.g., a protective tube). The protective tube must
have an excess length of approx. 25 cm above the concrete foundation.
·
Mounting the column on asphalt is not allowed!
Document: Rev. 1.00 / Document No.: 90333 │ Date 21.08.2018
WARNING!
!
Electrical hazard!
The V2/V3 floor-mounted column
must always be fitted with two
charging stations! There can be no
open cable openings in the column.
|3