AlphaESS SMILE-G3-B5 Puesta en servicio del hardware - Página 8
Navegue en línea o descargue pdf Puesta en servicio del hardware para Almacenamiento AlphaESS SMILE-G3-B5. AlphaESS SMILE-G3-B5 18 páginas.
8
The safety regulation must be set correctly
If you select a safety regulation which is not valid for your country and purpose, it
will cause a disturbance in the energy storage system and lead to problems with the
grid operator. When selecting the safety regulation, you must always observe the
locally applicable standards and directives as well as the properties of the PV system
(e.g. PV system size, grid-connection point).
If you are not sure which safety regulation is valid for your country or purpose,
please contact your grid operator for information on which safety regulation is
to be configured.
1.3.2. Direct Commissioning on WiFi configuration
You can commission the system during the WiFi configuration process directly.
1.3.2.1 Check the Running State without PV and Battery
Keep the PV switch of the energy storage inverter and AC breaker
of the PV-inverter off. Don't power on the batteries.
Turn on some larger loads directly connected on the grid to
check the grid status, the inverter LED ("Fault") will be red, don't
worry, because the battery is not communicated. The grid power
should be positive. Otherwise please check the direction of grid
CT or grid meter installation.
1.3.2.2 Check the Running State of PV and Battery
Switch off the AC breaker between the grid port on the energy storage inverter
and the grid, and switch off the AC breaker between the backup port on the
energy storage inverter and the loads.
Press the battery button. If there are more than one battery, press the button of
each battery and the interval time of powering on any two batteries should be less
than 5s.
Switch on the AC breaker between the grid port of the energy storage inverter
and the grid.
Commissioning Procedures