7.

CONTROL AND COMMISSIONING

7.1.

PREPARATION FOR COMMISSIONING

Please note that, on request by the Aermec
customer or the legitimate owner of the machine,
the units in this series can be started up by the
AERMEC After-Sales Service in your area (valid only
on Italian territory).
The start of operation must be scheduled in advance
based on the timeframe for the completion of works
for the system. Prior to the work to be carried out
by the AERMEC service personnel, all other works
(electrical and hydraulic hook-ups, priming and
bleeding of air from the system) must have been
completed.
Before starting the unit make sure that:
All safety conditions have been
1.
respected
The unit is correctly fixed to the support
2.
surface
3.
The minimum technical spaces have
been respected;
The hydraulic connections have been
4.
made respecting the inlet and outlet
5.
The hydraulic plant has been loaded and
bled.
6.
The hydraulic circuit cocks are open
The electric connections have been
7.
made correctly
8.
The voltage is within the tolerance of
10% of the unit nominal value
9.
Earthing is correctly made. All electric
and hydraulic connections are correctly
tightened.
7.2.

MACHINE COMMISSIONING

- Close the electric control board hatch.
- Position the appliance door-lock isolating switch
at ON,
turning the handle downwards.
- Press the ON key to switch the machine. When
the LED is on the unit is ready for functioning.
7.4.

ELECTRICAL DATA

POWER SUPPLY
WRL / WRL-H
180
200
400
Data declarated with No Pump version.
12
IWRLI2_13.04_5890700_00
7.3.

SEASON CHANGEOVER

- For every season change, check that the
functioning limits lie within the limits.
- Check that the compressor input current is lower
than the maximum indicated in the technical data
table.
- Check, that in models with three-phase power
supply, that the compressor noise level is not
abnormal. If this is the case, invert a phase.
- Make sure that the voltage value lies within the
pre-fixed limits and that unbalance between the
three phases (three-phase power supply) is not
above 3%.
7.3.1.
SEASON CHANGEOVER FROM PANEL
ON MACHINE
How to activate season changeover:
Under the On- Off branch it is possible change the
functioning mode of the machine. In the second
selection line (can ONLY be edited if OFF was
selected in the first line) it is possible to select the
seasonal state of the heat pump
(SUMMER, WINTER, DHW ONLY). Clearly according
to the machine configured and according to the
accessories installed.
NOTE:
ALWAYS REFER TO THE PROCEDURE
ILLUSTRATED IN THE USE MANUAL.
LRA [A]
230/3/60
222
460/3/60
116
575/3/60
90
230/3/60
276
460/3/60
147
575/3/60
96
230/3/60
357
460/3/60
177
575/3/60
133
For electric connections, use the cables with
double isolation according to the Standards in
force on this subject in the countries where the
unit is installed.
Commissioning must be performed with
standard settings. Only when the inspection
has been completed can the functioning Set
Point values by changed.
Before start-up, power the unit for at least
12-24 hours positioning the protection magnet
circuit breaker switch and the door lock
isolating switch at ON
Make sure that the control panel is off in order
to allow the compressor sup oil to heat.
On-Off/ Mode
Heat Pump Unit
ON
SUMMER + DHW
MOP [A]
MCA [A]
69
99,8
34
48,6
26
36,5
84
120,7
47
67,2
34
48,1
129
185,7
58
83,5
52
73,7
Recom. Fuse [A]
90
45
35
110
60
45
175
80
70