CORNING 1LAN-QSFPP-40GB-LR Manuel d'installation rapide - Page 6

Parcourez en ligne ou téléchargez le pdf Manuel d'installation rapide pour {nom_de_la_catégorie} CORNING 1LAN-QSFPP-40GB-LR. CORNING 1LAN-QSFPP-40GB-LR 13 pages. Head end equipment

CORNING 1LAN-QSFPP-40GB-LR Manuel d'installation rapide
ONE SD-LAN Head
End Equipment
Quick Installation Guide
SD-LAN-000-HEEQUIP
3 Application Host/SDDP
Top Of Rack (TOR) Switch Set Up
Using SD-LAN as Router |
RD
3
Virtual App Host / Se rver
p/n:
1LAN-D600E05-BL
3.1 Virtual Application Host Connections
Step 1
Connect power to Virtual Application
Host
Step 2
Connect a CAT 6 jumper into RJ-45
data port on the right side located on
the back of Virtual Application Host.
Connect other end of jumper to WAN
connection
Power
To SDDP
TOR
Console
Qucik Installation I SD-LAN-000-HEEQUIP
Examples:
IPTV
WIFI
SECURITY
IP PHONE
BMS
Etc.
p/n:
1LAN-SRV-50195L
p/n:
1LAN-SDDP-48P
SFPs:
1LAN-SFP-4305BC
Bi-Di SFP, 1 Gb
to ONT
1LAN-QSFPP-40GB-LR
40Gb SFP
1LAN-SFPP-10GB-LR
10Gb SFP
1LAN-SFP-1GB-LXLH
1Gb SFP
1LAN-SFP-1GCU
Cu SFP
1LAN-OA-UPC
To WAN
To SDDP
TOR
Step 3
Using a CAT 6 jumper plug into
RJ-45 data port to the left of WAN
connection on the back of Virtual
Application Host and route to SDDP
TOR switch in rack using horizontal
and/or vertical management in rack
Step 4
Using included console cable,
connect serial end of cable to serial
port on the back of Virtual Application
Virtual Application Host and route to
SDDP TOR switch.
3.2 SDDP TOR Connections
Step 1
Connect power to SDDP TOR Switch
Step 2
Insert a Copper SFP (1LAN-SFP-
1GCU) into one of the SFP ports of
the SDDP TOR switch
Step 3
Connect the Cat 6 jumper coming
from the left side RJ-45 data port on
the Virtual Application Host into the
copper SFP in the SDDP TOR switch
Step 4
Connect Micro USB end of console
cable coming from the back of Virtual
Application Host to the Console port
on the front of the SDDP TOR
1LAN-SFP-1GCU
To SDDP TOR
Console Port
(Micro USB)
| Page 6