AMES 672GD-19 Panduan Pemasangan, Pengoperasian, dan Pemeliharaan - Halaman 4

Jelajahi secara online atau unduh pdf Panduan Pemasangan, Pengoperasian, dan Pemeliharaan untuk Unit Kontrol AMES 672GD-19. AMES 672GD-19 12 halaman.

AMES 672GD-19 Panduan Pemasangan, Pengoperasian, dan Pemeliharaan
STEP 3
Manually operate the float linkage mechanism, allowing for the
main valve to respond to the pilot. Lift float linkage to stop, ensure
valve closes.
STEP 4
Adjust Upper stop if main valve action allows the tank level to be
higher than desired. When tank is full, valve starts closing (See
Figure 2).
STEP 5
(If Installed) Open Opening Speed Flow Control Adjustment:
The Opening Speed Flow Control allows free flow into the cover
and restricted flow out of the cover of the main valve.
If valve opening is too slow, turn the adjustment screw OUT,
counterclockwise (See Figure 3B), increasing the rate of opening.
If valve opening is too quick, turn the adjustment screw IN, clock-
wise (See Figure 3A), decreasing the rate of opening.
4
IOM-A-ACV-972-19_672-19 2115
Upper Stop
F10-13 - Float Control Pilot in Tank
Clockwise to DECREASE
rate of opening
3A
EDP# 1917110
Figure 2
Counterclockwise to INCREASE
the rate of opening
3B
Figure 3
Flow Control
© 2021 Watts