Step 1 (no picture). If the regulator is installed in service perform the following shutdown procedure.
Shutdown
Installation arrangements may vary, but in any installation it is important that the valves be opened or closed
slowly and that the outlet pressure be vented before venting inlet pressure to prevent damage caused by reverse
pressurization of the regulator. The following steps apply to the typical installation as indicated.
1. Open valves downstream of the regulator.
2. Slowly close the upstream shut-off valve.
3. Inlet pressure should automatically be released downstream as the regulator opens in response to the
lowered pressure underside of the diaphragm.
4. Close outlet shut-off valve.
5. Carefully vent any remaining internal downstream pressure.
remove bolts
Step 2. Remove the two 1/2-inch / 13 mm bolts which hold
the lower casing to the body.
old balanced
port assembly
Step 4. Remove the old balanced port assembly from the body; make sure to rotate the assembly toward the outlet
of the body as it is being removed to clear the pitot tube from the body. Take caution not to nick the orifice during
this process.
2
lift upwards
Step 3. Separate the lower casing from the body.
rotate assembly
toward the outlet
pitot tube