Dell M3UX16 Panduan Memulai - Halaman 6
Jelajahi secara online atau unduh pdf Panduan Memulai untuk Server Dell M3UX16. Dell M3UX16 32 halaman. Servers for sap hana
Connect the server to the power supply
Prerequisites
The site power breaker must be OFF when the Power Distribution Unit (PDU) is connected. The site power supply must remain
OFF until the system is ready to be powered on.
About this task
For each server module, perform the following steps:
Steps
1. Locate the power supply connections of each server module.
Figure 1. Power supply connections - rear view
2. On a S5416 server, locate the power supply connections of the UBox.
Figure 2. Power supply connections of the UBox - rear view
3. Connect the module to the PDU:
a. Route each power cord along the cabinet flange to the PDU.
b. Plug each power cord into the required PDU.
6
Connecting the Server
Connecting the Server
1