9. Remove the mounting plate from the door operator.
10. Remove the wires from the capacitor along with the wire previously connected to –VS from the
negative [-] terminal of the rectifier and pull them out. The capacitor is left out of the circuit.
11. Place the ORANGE wire supplied with the ECI 1000U LCD board onto the positive terminal [+]
of the rectifier.
12. Replace the mounting plate.
13. Connect the ORANGE wire from the + terminal of the rectifier to 54P pin of the 6 pin
connector for the ECI 1000U LCD board.
14. Install the ECI 1000U LCD board and connect 4 pin MOLEX connector to X1 for F1, 16V1,
16V2, L1A.
15. Connect the Molex connectors from the CAM switches to the connectors of the ECI 1000U LCD
board. The 15 pin Molex connector should be mounted with PIN 1 closest to the corner of the
ECI 1000U LCD board. Pin 16 is not used.
16. For 110/120VAC inputs from the controller jumper L1A to COM and F1 to 24B of the 5 pin
connector for those signal of the ECI 1000U LCD board.
17. Ensure the TEST/RUN switch is in the TEST position and the OPEN/CLOSE and
NUDGE/LOCK switches are in CENTER positions.
18. Connect 2 pin connector with L1A and L2A to ECI 1000U LCD board.
19. Perform Section 8 Initial Power up and Adjustments.

7.3 Replacing the ECI Canada ECI-1000-1400 with the ECI 1000U LCD board

1. Switch power to the door operator off and wait for the capacitors to discharge.
2. Remove the cover to access the door board
3. Unplug all connectors from the existing board.
4. Unscrew the four nuts holding the existing board in place and remove board.
5. Install the ECI 1000U LCD board and secure board in place.
6. Plug in all connectors
7. Connect the ground wire toX13 pin 1 (unlabeled pin)
8. Ensure the TEST/RUN switch is in the TEST position and the OPEN/CLOSE and
NUDGE/LOCK switches are in center positions.
9. Perform Section 8 Initial Power up and Adjustments

8 Initial Power up and Adjustments

8.1 Testing Operation

1. Disconnect connector X13
2. Ensure the Nudge/Lock switch is in the center position, the TEST/RUN switch is in TEST and
the OPEN/CLOSE is in CENTER position.
3. Apply Power to Door operator. The MAIN MENU screen should appear in the display
4. Select the DIAGNOSTICS menu.
a. The VBUS voltage should be 54VDC +/-10%
b. DRIVE and MOTOR readings should be 0
5. With the TEST/Run switch in TEST set the OPEN/CLOSE switch to the OPEN position.
ECI 1000-U LCD Installation Manual
Electronic Controls, Inc.
7073 North Atlantic Ave. Cape Canaveral, FL 32920
800-633-9788
www.eciamerica.com