Aeon Labs Aeotec Manual - Halaman 2

Jelajahi secara online atau unduh pdf Manual untuk Sistem Keamanan Aeon Labs Aeotec. Aeon Labs Aeotec 9 halaman. Home energy meter
Juga untuk Aeon Labs Aeotec: Panduan Pengguna (7 halaman), Panduan Pengguna (11 halaman)

Aeon Labs Aeotec Manual
Prepare for Installation / Reset
Please read the user manual before installing the product.
In order to include (add) a Z-Wave device to a network it must be in factory default state. Please make sure to reset the device into factory default. You can do
this by performing an Exclusion operation as described below in the manual. Every Z-Wave controller is able to perform this operation however it is recommended
to use the primary controller of the previous network to make sure the very device is excluded properly from this network.
Reset to factory default
This device also allows to be reset without any involvement of a Z-Wave controller. This procedure should only be used when the primary controller is inoperable.
- Press and hold the button on the backside for 10 seconds
Safety Warning for Mains Powered Devices
ATTENTION: only authorized technicians under consideration of the country-specific installation guidelines/norms may do works with mains power. Prior to the
assembly of the product, the voltage network has to be switched off and ensured against re-switching.

Installation

Unless otherwise stated, the circuit box's main breaker should be turned off to perform these installation steps.
1. Turn the main breaker off.
2. Open the main circuit box panel.
3. Clip one clamp of the meter around the incoming electricity cable that connects to the main circuit breaker.
4. Connect the clamp to the meter using a Clamp Connector.
5. Connect the AC Wire to the meter using the AC Wire Connector.
6. Wire the AC Wire into one breaker. The brown wire is Live, the blue wire is neutral.
7. Replace the main circuit box panel.
8. Turn the main breaker back on.
It is now time to place the main body of the Home Energy Meter. Inside the meter is a radio antenna used for communications, and this must be taken into
consideration when selecting a location for the meter.
If the circuit boxes is made of metal the radio signal strength may be reduced. In this situation it is recommended that the main body of the meter be affixed outside
the circuit box. This will improve the radio signal strength. The Home Energy Meter has been weatherized to the international IP43 standard so that it is resistant to
rain and snow when placed vertically with the wires protruding from the bottom of the unit.
To place the Home Energy Meter:
1. Unslot the backing plate from the back of your meter.
2. Affix the plate to the selected wall space using the provided screws.
3. Attach your meter to the backing plate.