ABB ACH580 Series Panduan Memulai dengan Cepat - Halaman 7
Jelajahi secara online atau unduh pdf Panduan Memulai dengan Cepat untuk Unit Kontrol ABB ACH580 Series. ABB ACH580 Series 15 halaman. Floating point control
Juga untuk ABB ACH580 Series: Cara Menyiapkan (2 halaman)
![ABB ACH580 Series Panduan Memulai dengan Cepat](/uploads/products/server2/67000/67000.jpg)
Check the direction of the motor.
If it is forward, select Yes, motor is spinning forward and
press
(Next) to continue.
If the direction is not forward, select No, fix direction and
press
(Next) to continue.
The first start is now complete and the drive is ready for use.
Press
(Done) to enter the Home view.
The Home view monitoring the values of the selected signals
is shown on the panel.
You can complete the commissioning in five different ways:
• Start using the drive with no further adjustment:
Press the Hand key
Hand
• Assistant commissioning:
Go to Menu → Primary settings → Start, stop reference and complete the two assistants. For more details
see the Firmware manual.
• HVAC quick commissioning:
Go to Menu → Primary settings → HVAC quick setup. Go through the items on the menu. This option is
instructed in the rows below.
• Commissioning with Primary settings:
Go to Menu → Primary settings. Set the start/stop and reference, motor data, ramps and limits. You can
continue with further adjustment. See in the Firmware manual or press the
menu items.
• Commissioning with parameters (advanced users only.):
Go to Menu → Parameters → Complete list. See chapter Parameters in the Firmware manual.
HVAC quick commissioning
2 – Completion of commissioning
on the panel to start the motor, and set the reference on the panel.
EN – Quick start-up guide 7
information on Primary settings
EN