SURFACE MOUNTED
INSTALLATION
Ensure power is turned off and remove luminaire from packaging.
Housing
Screw the housing on the ceiling
tightly and insert the light module
into the housing.
Put the end caps and secure them
with the screws. Connect power to
mains supply and test the luminaire
for correct operation and switching.
1. Push the connect plate on the first
fixture and tighten.
2. Insert light module into the housing.
Connect
Plate
3. Push the housing of
the second fixture to
the connect plate.
4. Insert light module
into the housing.
Open hole
Accurately mark and screw hole.
Screw
Screws
5. Plug terminals into
the same colour and put
the fixtures together.
6. Screw the connect
plate into the second
fixture.
*Continuous Run installation
216 / 516 / 1116 cm
Plastic
Expansion
Screws
Electric
drill
Mounting Nut
Screw
Screw the mounting nut onto the
ceiling tightly. Fix the suspension
rope through the mounting nut and
adjust height (before hanging fixture).
End Cap
Install the fixture to the suspending
rope by screwing to security nuts of
the suspension rope. Connect power
to mains supply and test the luminaire
for correct operation and switching.
1. Install the second light as the previous steps.
2. Loosen the screw and take down the End Cap
to take out the reserved embedded terminal.
End Cap
AC Input
Wire
SUSPENDED
INSTALLATION
Plastic
hammer
Press button below and pull rope
to adjust height. Cut excess
Security
Connect
Plate
3. Push the connect
plate on the first
fixture and tighten.
4. Push the housing
of the second fixture
to the connect plate.
Nut
5. Plug terminals into
the same colour and put
the fixtures together.
6. Screw the connect
plate into the second
fixture.