2.1 Principle of operation
Road
tanker
WARNING
Do not operate
without guard
in place.
2.1.1 Unloading :
• Ground the vehicle.
• Connect the Centrex multi 2 unit to the compartment to
be emptied via a DN80 hose. Then open the valve.
• Select the storage tank to be filled.
• If necessary, reset the meter to 0 and put a ticket in the
printer.
• Starting-up of the pump.
• The product passes through the pump filter 1.
• The filter 4 allows to protect the meter.
• The gas separator 5 allows the air produced to be eva-
cuated in case of stock shortages.
• The sight glass 6 allows checking that the gas separator
works properly (no continuous flow of liquid).
• The degassing line 7 carries out the gas caught by the gas
separator and move them after the meter in the discharge
line.
• The no return valve 16 avoids any liquid return from going
back to the gas separator.
• The setted valve 8 allows the degassing of the product
and prevents its return to the pumping zone.
• The degassed product passes into the meter 14 with data
recorded on the ticket or via electrical signals depending
on the version.
• Once the compartment is empty, the assembly will fill
with air and the meter will stop.
NT 1006-C00 03 18 Centrex Multi 2 e
2. GENERAL DATA
CENTREX MULTI 2
OPERATION WITHOUT THE SHAFT
PROTECTOR CAN CAUSE SERIOUS
PERSONAL INJURY, MAJOR PROPER-
TY DAMAGE OR DEATH.
1
Pump filter
2
CC8-65 pump
3
Pressure gauge
4
Meter filter
5
Gas separator
6
Sight glass
7
Degassing line
8
Check valve setted 1 bar
9
Valve
10
Product recapture filter
11
Check valve
12
Valve
13
Drainage pipe
14
Meter
15
Check valve setted 0,1 bar or 0,4 bar
16
Check valve
• If the next compartment contains the same product,
connect the DN80 hose to it without stopping the pump.
• If the next compartment contains another product :
- Lift the DN80 hose to drain it and wait for the meter
to stop and the gas separator sight glass 17 to
empty.
- Print the ticket where necessary and reset the meter
to zero.
- Select the new storage tank to be filled.
- Put a new ticket in the printer.
- Connect the DN80 hose to the new compartment.
• Proceed in the same manner for the other compartments,
lifting and draining the DN80 hose before stopping the
pump.
• Refit the DN80 plug on filter 1.
5/11
Storage
tank