maximum position of the profile plate. In actual operation, the differential pressure
switch is usually set to detect the process air pressure difference before and after the
burner profile plate.
3. Start the combustion air fan, adjust it to 100% of the flow rate, measure the pressure
difference between the combustion air and the downstream of the burner, the design
DP is 2-2.5 mbar.
4. Modulate through full range of burner input capacity, check the air DP and combustion
air flow.
5. For dry run test, first close the manual valve closest to the burner, then start the control
program, and start the dry test of the burner. Doing such a dry test can check all the
interlocking conditions in the combustion system, such as gas pressure switches, air
pressure switches, and leak test system.
6. Then carry out the pilot burner commissioning; procedure is carried out until reliable
ignition is achieved and the flame signal of the pilot ignition can feed back to the flame
controller with stable flame signal. During ignition test, the gas valve before burner
should be closed.
7. After the stable ignition is established, open the gas valve before burner.
8. First, setup low fire. At this time, the control system should be set in the manual mode,
which is set by adjusting to the minimum firing position. The gas volume at this position
requires the flame to propagate across sectional area of the burner, that is, all modules
will be firing. The flame detector detects the far end of the burner. Since the flame
propagate to the far end of burner will take time, the time setting of the flame relay
can be adjusted at this moment, to make sure both flame detectors will be active to
monitor flame after the delay time is over.
9. The relevant pressure and gas flow values need to be recorded during the
commissioning process.
10. Then set the high fire rate. This is achieved by using the manual control of the process
controller driving the modulating gas valve open step by step. Each step of the ramp up
to the maximum rate being monitored, gas flows recorded as not to exceed the
required rate. On reaching the fully open position, the main gas pressure regulator can
be set to give the required heat capacity.
11. After the high fire is set, low fire position should be checked again for fire rate and
reliable ignition. This can be cycled couple times to ensure low fire-high fire-low fire-
high fire firing stable.
12. All pressure switches shall also be tested by reducing or increasing the setpoints until
system trip. Relevant alarm procedures and control logic checked. Trip positions
recorded and normal operation setpoints selected and set.
Note: The above procedure will be carried out by using the process air flow.
12.1
Start burner
After all firing rate is setup, the burner gets into operation mode, the gas flow control
valve is controlled by 4-20 mA from temperature controller. The pilot burner could be
closed or run continuously according to the design requirements.
Anderson Thermal Soluions(Suzhou)Co. Ltd.