V. Assembly step
All parts of electric treadmill have been strictly assembled and debugged before the ex works. An electric
treadmill can be easily assembled into if the installation is carried out by observing following steps.
Step I: Install upright pole: Open the packing box (box
B) and then bring out the treadmill. Firstly, lock the left
upright pole on the treadmill frame in 2 M10×20 and 2
M10×30
round
head
(containing shim); secondly, connect the right upright
pole (control line is provided in the upright pole) with
the control line reserved on the control line; then,
insert the connector of the control line into the
wire-through hole of the right upright pole; finally, lock
the right upright pole on the treadmill frame in 2
M10×20 and 2 M10×30 round head hexagon socket
screw (containing shim), as shown in the figure below:
Step III: Install screen: Open the packing box and
then take out the screen. Firstly, connect the wire of
the screen with that of the meter head in one-to-one
way; secondly, insert the screen into the meter head;
finally, lock the screen on the meter head in 4 M6×25
hexagon socket head cap bolts (containing shim), as
shown in the figure below:
hexagon
socket
screw
Step II: Install meter head: Open the packing box (box
A) and then bring out the meter head. Firstly, connect
the control line in the right upright pole with that at the
lower right of the meter head; secondly, insert the
meter head into the left and right upright poles; finally,
lock the meter head on the left and right upright poles
in 6 M8×16 hexagon socket pan head screw
(containing shim), as shown in the figure below:
Step IV: Install the decorative elements of upright pole
and lower meter: Firstly, fix the decorative elements of
left and right upright poles at the treadmill in 6 M8×8
large crossed flat head screw; secondly, fix the
decorative elements at lower left and right of the
meter on the left and right upright poles below the
meter head in 2 M4×8 large crossed flat head screw
and 4 M4×10 round head tail-cut tapping screw, as
shown in the figure below:
-6-
M4×10 round head
tail-cut tapping
screw
M4×8 large
crossed flat
head screw