3-in-1 Sensor Installation Guidelines
INSTALLATION HEIGHT
(higher is better for wind measurement) in an open area. Secure to fence post, 2"x4"
wood, 3/4" pole, etc. (not included)
LEVEL INSTALLATION
accurate wind measurement.
Top or Side Mount
1. Insert the mounting base into the
hole on the bottom of the sensor.
2. Use one of the screws included
in the hardware bag to fasten
the lower sensor housing to the
mounting base.
3. Fasten mounting base to a post or
railing using 2 screws.
Pole Mount
1. Insert pole (we recommend 3/4" schedule
40 PVC / 25.8 mm O.D., not included)
or similar item all the way into the hole on
the bottom of the sensor. Note: Mounting
base is not used.
2. Use one of the screws included in the
hardware bag to fasten the lower sensor
housing securely to the pole.
The 3-in-1 sensor is now ready to use.
Clear Data Collected During Installation
When installation is complete, clear erroneous data from the display unit by pressing
the "CLEAR RECORD/RESET" button for each category, on the back of the display
inside the battery compartment.
Basic Setup is Complete
The 3-in-1 sensor will now synchronize with the display unit. It may take a few
minutes for synchronization to complete. If both or one of the units appear to be
functioning improperly, please refer to the troubleshooting section.
Mount the sensor at least 5 feet (1.5 meters) off the ground
Use a bubble level (not included) to ensure level installation for
Top Mount
10
Side Mount
Pole Mount
Do not install during
electrical storms.
Do not place pole
or sensor near
electrical lines or
electrical equipment.