ClearWater mineralpure R-50 Manuale di installazione - Pagina 5

Sfoglia online o scarica il pdf Manuale di installazione per Sistemi di filtrazione dell'acqua ClearWater mineralpure R-50. ClearWater mineralpure R-50 16.

E). INSTALLING THE ELECTRODE FLOW CELL TEE
1.) Locate a space for the electrode flow cell tee (the 2" slip/slip/threaded tee). The tee should be
installed after the pump and either before or after the filter. After the filter is preferred, but it will
work fine if installed before the filter. NEVER INSTALL THE TEE NEXT TO THE POOL'S
HEATER.
2.) Turn off the pump and close all valves. Disconnect all sources of power going to the timer or
pump.
3.) Using a hacksaw or backsaw, cut a 4-inch gap in the section of pipe if 1 1/2" pipe exists, or cut
out a 3" gap if a 2-inch pipe exists.
4.) Sand the burrs off the pipe. Dry the pipe and clean the ends with PVC primer/cleaner.
5.) If 1 1/2" pipe exists, cement the 2" to 1 1/2" reducer bushings into the tee (included with the unit).
6.) The tee should be mounted on the return line after the pump and mounted slightly downward so that no air-pocket
can form in the electrode chamber (below a horizontal position). THIS IS EXTREMELY IMPORTANT. If there is
not enough "give" to allow insertion of the tee, install unions.
F). INSTALLING THE ELECTRODE
Generously wrap Teflon tape around the threaded part of the electrode assembly several
times. Screw electrode into the tee. Do not over tighten.
G). MOUNTING THE CONTROL BOX
Mount the control box on the wall within six feet of the electrical source and ten feet of the electrode flow cell tee.
5