- ページ 4

リフティングシステム Floe PWC1300のPDF クイック・スタート・ガイドをオンラインで閲覧またはダウンロードできます。Floe PWC1300 8 ページ。 Anchoring system
Floe PWC1300 にも: 組立説明書 (12 ページ)

Plastic end caps
Side Frame
Rear Frame
Beam
3/8" x 2" bolt
Leveling Leg
Side Frame
Fig. 1B
Front Frame
Beam
Fig. 1
Slide clamp tight
against locating plate
Sheet 4 of 8
Unscrew 3/8" x 3/4" bolt from leveling legs.
Lay side frames on side. Insert leveling
legs into corner posts making sure the nut
track lines up with lower hole in corner post.
Line up the nut and washer with the hole in
corner post and fasten with 3/8" x 3/4" bolt
that were removed from leveling legs. Leave
leveling leg extended out 8". See Fig. 1 Torque
to 40 ft. lbs.
Clamp front and rear frame beams to side
frames using 3/8" x 2" bolts and nylock nuts.
Torque to 40 ft. lbs. Frame beams to be
located as shown in Fig. 1A and 1B.
3/8" x 3/4"
Adjusting bolt
Fig. 1A
Fig. 1A
Front Frame Beam
Step 1

IMPORTANT NOTE:

Be sure that the drainage holes in the
frame beams are on the bottom at
time of installation.
Slide clamp tight
against locating plate
Fig. 1B
Rear Frame Beam