Mechanical Commissioning and Air Purge

11.
This procedure outlines how to perform a mechanical operational test and making sure that
the dispenser is functioning correctly. Before testing the unit, check for any damage that may
have occurred in transit. Check all terminals, plugs, and chips to make sure that they are
securely in place.
To test the unit please carry out the following tests:
1.
Make sure that the electrical commissioning tests have been carried out and the solenoid
operation has been verified before carrying out the following tests.
2.
Slowly open the fuel supply valves to the dispenser, checking for any leaks.
3.
Turn on the power supply to the dispenser.
4.
Lift the nozzle (80 LPM side) or turn switch to ON (400 LPM side).
5.
The display will show 888888 and the solenoids will energise, starting the pump motor.
Check that Diodes D8, D10 and D11 turn on, indicating a signal is being sent to the triacs
to open the solenoid valves
6.
Check all the dispenser fittings, solenoids and pipework for leaks.
7.
Slowly dispense fuel from the dispenser, being careful to shield yourself from splashes as
there may be air in the fuel causing it to spray from the nozzle.
8.
The display and tote should increment when fuel is flowing.
9.
The dispenser can now be calibrated. Refer to the C4000 Master Manual for calibration
instructions.

Setting up the C4000

12.
Once the pump is connected on site, the final setup check and calibration to complete the
installation must be carried out, using the Parameter Switch and Calibration (K-Factor) Switch.
These switches are found on the C4000 Microprocessor Board which is housed in a metal
enclosure located on the left front of the unit below the display panel

Configuration Codes

12.1
The configuration code has been set at Compac and should not be changed
In the event of it being lost and having to be re-entered the configuration is written on the
yellow label on the C4000 processor board cover

Submersible Delay (Sd)

12.2
This is the time delay from when the Submersible pump starts to when the solenoids in the
dispenser open to allow time for the leak detector to reset.
This is factory set by Compac at 005 (five seconds).
If problems are experienced with the leak detector tripping, firstly check that 'Sd' is still set
and then, if necessary, make it longer as follows.
1. Press and release the K factor switch repeatedly until 'Sd' appears on the Dollar display
'dXXX' will appear in the litres display.
2. Continue to press the K factor switch until the number to be changed flashes. Hold the
switch down and this number will then increment.
3. Release the switch when the required number is displayed. The value of the displayed
number will then be stored in the C4000 memory as the Submersible delay.
\\Cilaklfs1\shrdata\Masters\Installation Sheets\Master & Premier\MMR400-80S Installation
Sheet.doc