D.START UP SEQUENCE
When the unit is switched on it will first run through a period of system checks.
During this time the display will show various system parameters before the fan motor
starts. After 10 seconds the product will be ready for commissioning.
E. COMMISSIONING
Accessing the Commissioning Menu
If the fan is powered and the display is not lit, then press any button to access the
menu. After 30 seconds without menu activity the display will switch off; any new
settings will then be applied.
There are three buttons on the front of the unit:
 
 
 
-
+
 
SET
The + button is used to increase the value of a setting, the – button is used to
reduce the value of a setting and the SET button moves to the next menu item.
Commissioning Menu Structure
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 