- ページ 3

産業用電気機器 Abtech HVJB SeriesのPDF 設置、操作、メンテナンスの説明書をオンラインで閲覧またはダウンロードできます。Abtech HVJB Series 4 ページ。

Abtech HVJB Series 設置、操作、メンテナンスの説明書
INSTALLATION, OPERATION & MAINTENANCE INSTRUCTIONS FOR
ABTECH 'HVJB' series – SIRA06ATEX4280
??
ABTECH
www.ab-tech.co.uk
A B CONTROLS & TECHNOLOGY LTD SHEFFIELD S9 2UA ENGLAND
HVJB __________ *** W ___kV
SERIAL No.
S*****
II 3 GD-IP66 - T70 C EEx nA II T4
SIRA06ATEX4280
WARNING! ISOLATE ELSEWHERE BEFORE OPENING
CABLE AT ENTRY POINT EXCEEDS 70 deg C
Installation
1) Using the mounting dimensions data provided, either in the product catalogue data sheets or
on the drawings supplied, (as part of the project documentation), mark out the positions for the
mounting holes on the surface where installation is required.
2) Drill the mounting holes for either M8 or M9 fixing studs.
3) Insert the top two studs leaving 8 to 10mm protruding and lift the enclosure into position using
such assistance as may be necessary to avoid injury and hang the top fixing brackets of the
box onto the studs. Ensuring that the box is secure, insert and tighten the bottom two studs.
Now complete tightening the top two studs.
4) Unfasten the lid securing screws and remove the enclosure lid. Put the lid in a safe place.
5) Install and secure the cable glands in accordance with the manufacturers instructions.
6) Remove the top half on each cable clamp and put safely aside.
7) Remove the terminal post lock nuts, washers and the upper current bars and put safely aside.
8) Pull the cables into the box leaving trailing leads long enough to reach their respective crimp
lugs after routing through the cable clamps.
9) Trim each cable core so that the conductor end will reach the inside stop of the crimp lug on
which it is to be terminated.
10) Strip the insulation of each cable core by the length of the crimping barrel plus 2mm.
11) Remove each crimping lug in turn from the terminal post and place the securing nuts to one
side.
12) Crimp each lug onto the respective conductor ensuring that the crimp die set used is suitable
for the conductor size and is not damaged or excessively worn. The crimp die set may produce
either a hexagon type crimp or an indent type crimp. With hexagon die sets execute at least
two crimps on each lug.
13) The finished crimp should meet the tensile strength requirements of Table 2 of BS4579:Part
1:1970.
14) Route the cable core through the appropriate cable clamp and place the hole in the palm of the
now attached cable lug on to its respective terminal post, on top of the lower current bar.
15) Replace the upper current bar and secure it in place with the flat washer, spring washer and
two locknuts provided. Ensure that the spring washer is fully compressed by the first lock nut
then apply a further 1/8 to ¼ turn. Secure the fitting with the second lock nut.
16) When all the cable lugs have been attached and correctly tightened replace the top halves of
the cable clamps and tighten each one to secure the cables.
17) Replace the lid and secure it by closing the lid and tightening the lid fixing screws. Ensure that
all gland-plate securing screws are tightened.
?????
/ 20**
A B Controls and Technology Ltd
Sanderson Street, Lower Don Valley, Sheffield
ABTQ-74 rev 01 (Last review: 05 Oct 06)
Marking
The maximum power dissipation and
voltage permitted in this terminal box are
marked on the label and identified as
***W and __kV. The ambient temperature
range for which this product is suitable is
o
–20 to +40
C
1/2