7.
Reposition and secure control onto mounting
bracket.
8.
Install remaining end of interconnecting cord to
Automatic Weld Control according to its Owner's
Manual.
D. Connections For Carriage Movement Control
WARNING: Read and follow safety informa-
tion at beginning of entire Section 4-4 before
proceeding.
In normal operation, upon pressing the START button
the unit will immediately start welding, and the carriage
will immediately start moving; however, installing a Fix-
ture Start Delay switch, allows the operator to delay fix-
ture movement after the START button is pressed.
When a Fixture Start Delay switch is installed, the unit
will start welding when the START button is pressed, but
the carriage will not move until the Fixture Start Delay
SECTION 5 – CUSTOMER-SUPPLIED REMOTE CONTROL CONNECTIONS (Optional)
5-1.

REQUIRED EQUIPMENT

Several optional controls are available to enhance the
usability of the Sidebeam assembly. The Remote Pen-
dant Control provides remote control of the START/
STOP push buttons, TRAVEL SPEED control, and
TRAVEL DIRECTION and JOG DIRECTION switches.
If the Remote Pendant Control is not obtained, the Car-
riage Control wiring can be modified to accommodate
external (remote) switches for this control.
To install remote switches, read the following safety in-
formation and proceed to the appropriate switch sec-
tion:
WARNING: ELECTRIC SHOCK can kill.
Do not touch live electrical parts.
Shut down Carriage Control, Automatic Weld
Control, and welding power source, and dis-
connect input power employing lockout/tag-
ging procedures before inspecting, installing,
or adjusting.
Lockout/tagging procedures consist of remov-
ing input plug from receptacle, padlocking line
disconnect switch in open position, removing
fuses from fuse box, or shutting off and red-tag-
ging circuit breaker or other disconnecting de-
vice.
5-2.
CARRIAGE CONTROL REMOTE START AND
STOP
WARNING: Read and follow safety informa-
tion at beginning of Section 5-1 before
proceeding.
For Remote Start and Stop control, a momentary-
contact switch (or switches) or a maintained-contact
(relay) switch must be connected to terminal strip 1T in-
side the Carriage Control. Installing the momentary-
contact switch(es) does not disable the Carriage Con-
OM-889 Page 14
switch is closed, or the unit receives a command from an
external weld control.
To install the Fixture Delay switch, proceed as follows:
1.
Remove the four screws securing the Carriage
Control to the mounting bracket, and remove the
control from the bracket.
2.
Remove the securing screws from control wrap-
per, and remove wrapper.
3.
Locate terminal strip 1T, and remove jumper links
between terminals C and D and terminals K and L
on 1T.
4.
Connect a normally-open switch across termi-
nals D and L on 1T.
5.
Reinstall and secure control wrapper.
6.
Reposition and secure control onto mounting
bracket.
trol START and STOP push buttons; however, installing
a maintained-contact (relay) switch for Remote Start
and Stop control disables the front panel START push
button, but the STOP push button will function if the op-
erator keeps the button depressed. For example, if the
remote start switch is in operation, and the operator
presses the Carriage Control STOP button, the unit
stops all operation until the front panel STOP button is
released.
To make Remote Start and Stop switch connections,
proceed as follows:
1. Remove the four screws securing the Carriage
Control to the mounting bracket, and remove the
control from the bracket.
2.
Remove the securing screws from control wrap-
per, and remove wrapper.
3.
If installing a momentary-contact switch(es) for
remote start and stop control, proceed to Step 4.
If installing a maintained-contact (relay) switch,
proceed to Step 5.
4.
Install the momentary-contact start and stop
switch(es) as follows:
a. Loosen strain relief clamp on rear of control,
and route cord from switch(es) through clamp
to terminal strip 1T.
b. Remove jumper link between terminals M and L
on 1T.
c. Connect the two leads from the normally-open
start switch to terminals M and J on 1T.
d. Connect the two leads from the normally-
closed stop switch to terminals M and L on 1T.
5.
Install the maintained-contact (relay) switch as
follows: