by passing the cable through the DC cableglands (17). (FIG. 13).
- Confirm the DC cables have a 13-21mm diameter, a cross-section of
95mm² and are made of copper or aluminum.
- Unscrew the cable gland and remove the cap
- Run the cable through the cable gland (17)
- Connect the PV array (+ and -) to the DC input screw terminal block (39)
(tightening torque 20 Nm) (FIG. 14)
-When finished, confirm the polarity is correct for each string.
- Pull each cable to check its tightness.
37
INPUT
DC
OUTPUT AC
17
13
• PVS-50(60)-TL-SX and PVS-50(60)-TL-SX2 Models
In these inverter models, the PV array is connected to the inverter through
quick fit input connectors (MPTT) (19), (20), (21) located at the bottom of
the mechanics. (FIG. 15)
- Based on PV system configuration, inputs can be set as 3 independent
MPPTs or as a single MPPT with the three paralleled input channels.
Paralleled inputs can be obtained by installing the bar (provided) on
the paralleled MPPT connection points (41) using the 3 screws (M5x12,
tightening torque 4.0Nm) (FIG. 16) An incorrect setting of the input
channels can lead to loss of energy production.
- Quick fit connectors are divided into 3 groups (a group for each input
MPPT), each composed of 5 couples of quick fit connectors. Refer to
document "String inverters – Product manual appendix" available on
FIMER website https://www.fimer.com to find out the make and model
of the quick fit connector used on the inverter. Depending on the type
of quick fit connectors installed on your inverter, you will have to use
the same type for the corresponding counterparts (after checking for
compliant counterpart on the manufacturer's website or with FIMER).
41
INPUT
DC
19
1A
2A
3A
OUTPUT AC
1B
2B
3B
1C
2C
3C
20
1D
2D
3D
1E
2E
3E
21
15
WARNING –
The use of non-matching counterparts for the quick
B
fit connectors installed on the inverter may seriously damage the
inverter and invalidates the product warranty.
- Connect all strings to the appropriate
quick fit connectors (+ and -) following the
site wiring diagrams e check the tightness
of each Single connection. If some string
inputs are not used, ensure that caps are
installed on the connectors; install them if
missing. This operation is necessary for
the tightness of the inverter and to avoid
damaging the free connector that may be
used at a later date. (FIG. 17)
+
-
14
16
41
17
10. Instruments
Description of the LEDs located on the inverter cover:
POWER LED
GREEN On, if the inverter operates correctly.
Flashes in the network control phase or if the
sunlight is not enough.
ALARM LED
YELLOW The inverter has detected a fault. For
inverters with a display, the error/warning message
appears on the display.
GFI LED
RED Ground fault of the PV array, DC side. For
inverters with a display, the error message appears
on the display.
READ THE MANUAL –
E
of error/warning codes appearing on the display, for inverters with a
display.
11. Commissioning
ATTENTION –
Before
A
procedure, ensure that all the checks indicated in the previous
sections of this Quick Installation Guide have been correctly
performed and also that the front door 4 have been correctly
closed! Make sure irradiation is stable and adequate for the inverter
commissioning procedure to be completed.
Commissioning could be carried out in two different ways:
• Via "Installer for Solar Inverters" mobile APP - Recommended
mobile APP for commissioning single inverter as well as multi
inverter solar plant.
• Via Web UI (access point wireless network) - Integrated Web User
Interface enabling setting parameters and performing commissioning of a
single inverter (multi inverter support is not provided). Recommended as
alternative method for performing single inverter commissioning.
Commisioning via "Installer for solar inverters" mobile app
"Installer for Solar Inverters" is the new advanced FIMER mobile APP
allows to simplify commissioning, parameter settings and troubleshooting
of FIMER string multi-inverters in large scale solar plants.
Even in case of single inverter installation it can be consider the most
suitable professional tool to be used. "Installer for Solar Inverters" mobile
APP is available for mobile devices with an Android version of 6.0.1
or greather (iOS mobile devices support will come soon) and could be
downloaded and installed from Play Store.
Commissioning procedure:
• It's highly recommended to connect the inverters in ethernet daisy chain
(with or without ring) before executing the commissioning procedure.
Make sure that all the inverter being commissioned features the last
firmware version (updating can be executed via Installer for Solar
Inverters mobile APP).
• Supply the input voltage from the photovoltaic generator to the inverter.
ATTENTION –
Make sure irradiation is stable and adequate for the
A
inverter commissioning procedure to be completed.
The main steps to complete the commissioning procedures are
listed below:
• Installer for Solar Inverters mobile APP installed on mobile device.
• Enabled Aurora Vision installer account allowed to use the mobile APP.
The account can be created in the mobile APP directly following the
dedicated wizard procedure.
• Manual
claiming
of
the
The claiming process consists of indicating which inverters are to be
commisioned.
Claiming process can be executed by scanning the QR codes of all the
inverters being worked and putting the selected inverters into the working
list. Please insert in the list inverters belonging to the same inverters
family; no more than 40 inverters by time can be configured together.
Refer to the product manual for a description
starting
the
inverter
commissioning
inverters
to
be
commissioned.
6