3.

COMMISSIONING

3.1

Initial Preparation

3.2

Removing the Casing

B004
MTS (GB) Limited support the
find a copy of the
ence of your customer, they are shown how to us it, and it is signed by them. Please
instruct your customer that they must have their
ever they contact a service engineer or us.
Preliminary electrical system checks to ensure electrical safety must be carried out
by a competent person i.e. polarity, earth continuity, resistance to earth and short
circuit.
Filling the Heating System:
Remove the panels of the case and lower the control panel (see point 3.2. for
further information).
Open the central heating flow and return cocks supplied with the connection
kit.
Unscrew the cap on the automatic air release valve one full turn and leave
open permanently.
Close all air release valves on the central heating system.
Gradually open valve(s) at the filling point (filling-loop) connection to the
central heating system until water is heard to flow, do not open fully.
Open each air release tap starting with the lower point and close it only when
clear water, free of air, is visible.
Purge the air from the pump by unscrewing anticlockwise the pump plug and
also manually rotate the pump shaft in the direction indicated by the pump
label to ensure the pump is free.
Close the pump plug.
Continue filling the system until at least 1 bar registers on the pressure
gauge.
Inspect the system for water soundness and remedy any leaks discovered.
Filling of the D.H.W. System:
Close all hot water draw-off taps.
Open the cold water inlet cock supplied with the connection kit.
Open slowly each draw-off tap and close it only when clear water, free of
bubbles, is visible
Gas Supply:
Inspect the entire installation including the gas meter, test for soundness and
purge, all as described in BS 6891:1988.
Open the gas cock (supplied with the connection kit) to the appliance and
check the gas connector on the appliance for leaks.
When the installation and filling are completed turn on the central heating system
(sect. 3.4) and run it until the temperature has reached the boiler operating temper-
ature. The system must then be immediately flushed through.
The flushing procedure must be in line with BS 7593:1992 Code of practice for
treatment of water in domestic hot water central heating systems.
During this operation, we highly recommend the use of a central heating flushing
detergent (Fernox Superfloc or equivalent), whose function is to dissolve any for-
eign matter that may be in the system.
Substances different from these could create serious problems to the pump
or other components.
The use of an inhibitor in system such as Fernox MB-1 or equivalent is strongly rec-
ommended to prevent corrosion (sludge) damaging the boiler and system.
Failure to carry out this procedure may invalidate the appliance warranty.
1
F
FO23
initiative. Within the information pack you will
logbook. It is important that this is completed in the pres-
To dismantle the front part of
the casing, proceed as follows:
1. Loosen the two screws "F"
logbook with them when-
located on the bottom part
of the boiler until the
first thread on the screws
appears;