- ページ 8
室内装飾品 ClearSpan 200200SS1のPDF 取扱説明書をオンラインで閲覧またはダウンロードできます。ClearSpan 200200SS1 18 ページ。 Add-a-bay shade system
CLEARSPAN
SUNBLOCKER SYSTEM
™
LEG ASSEMBLY
Each leg assembly consists of one (1) drilled pipe, one (1)
5-way coupler, and required cap screws or bolts.
Gather the parts:
•
Drilled leg pipe (#2375120D) and 5-way coupler
(#103839)
•
Cap screw 3/8'' x 1'' (#FAG355B) and band clamp
(#103856)
1. Insert the plain end of a drilled pipe into the bottom
(odd) port of a 5-way coupler.
2. Secure the pipe in the 5-way coupler using 3/8'' x 1''
cap screws through the threaded holes of the coupler.
Cap Screws
(#FAG355)
NOTE: Install the drilled pipes with the plain end
inserted into the 5-way coupler. The drilled end of the
pipes are attached to ground posts or mounting feet if
used.
3. Assemble the legs until all drilled pipes and 5-way
couplers are used.
4. Slide a band clamp onto each leg assembly and
position it near the 5-way coupler. Slightly tighten the
band clamp or use tape to keep it in place.
NOTE: If *mounting feet are used, attach a foot to each
leg assembly using bolts and nuts at this time.
If *ground posts are used, drive the post into the
ground so the top of the post is 1' foot above the
finished grade. Refer to the MUST READ document
sent with the shelter. Use the Quick Start diagrams to
properly space the ground posts if used.
*Additional purchase required for mounting feet and
ground posts.
8
Visit www.ClearSpan.com for additional products and customer assistance.
RAFTER ASSEMBLY
The leg assemblies are connected with plain pipes to form
the rafters.
Gather the parts:
•
•
•
•
1. Select a plain 20' purlin assembly and slide two (2)
2. Slide each end of the purlin assembly into the through
5-Way Coupler
(#103839)
Leg Pipe
(Plain End)
3. Verify that the on-center width dimension measured at
4. Secure the plain pipe to the couplers using 3/8'' x 1''
5. Reposition the band clamps (previously installed on
Leg assemblies
20' purlin assemblies
Cap screw 3/8'' x 1'' (#FAG355)
Strut (#103838) and band clamp (#103856)
band clamps onto the pipe. This pipe connects two (2)
leg assemblies.
ports of the 5-way couplers as shown below and align
the pipe ends with the center of the 5-way coupler.
Rafter Assembly
Band Clamp
20' Purlin Assembly
Through Port
Leg Assembly
NOTE: Position the 5-way couplers so the through tube
is aligned with the width of the frame.
the 5-way couplers is 20'-3". Adjust as needed.
cap screws through the threaded holes of each coupler.
each rafter leg and the 20' rafter pipe) approximately
12" from the 5-way couplers.
NOTE: If the band clamps were not installed, install
them now. Use adjustable pliers to squeeze the clamps
back into shape after adding them to the pipes.
20'-3"
on-center
Revision date: 10.09.07