コントローラー Cutler-Hammer EATON Ampgard Mark VのPDF 取扱説明書をオンラインで閲覧またはダウンロードできます。Cutler-Hammer EATON Ampgard Mark V 12 ページ。 Solid-state, brush-type, synchronous motor controllers

I.B. 48008
AUTOTRANSFORMER STARTER OPERATION
The field power thyristors will be held OFF until the 115
VAC inhibit signal and the proper slip frequency have
appeared. The 2.5 to 3.5 second synchronizing period
also will not start until both these conditions are met.
When the controller is used in conjunction with a
reduced-voltage motor controller, the gating is inhibited
until full voltage is applied to the motor. This is done by
not applying 115 volts to terminal 115 and IN- on the
circuit board, until motor is at full voltage.
The field excitation must not be applied until an
autotransformer starter has been sequenced to full
voltage. If the field is applied before the starter has
transitioned to full voltage, a high current will result from
the voltage unbalance condition, and may cause physical
damage.
START-UP PROCEDURE FOR AMPGARD LINE-UP
Prior to start-up, verify a proper line-up installation, one
that is undamaged, free of skids, eyebolts, lifting angles,
debris, and all foreign material, one that is level and
securely mounted and properly wired. Confirm each
starter compatability with motor voltage, HP, and FLA.
Check the torque tightness of all connections. Study all
applicable instruction material and diagrams. Have
available the schematic and connection diagrams fur-
nished with the following equipment:
1. Dielectric (Hi-pot) tester capable of delivering 40
milliamps at 16 kVAC or 23 kVDC.
2. Multimeter to measure ohms and DC volts.
3. Meg-ohm meter (Megger) capable of producing 2500
volts.
Safety Check
Verify that the primary (medium-voltage) sources of power
to the Ampgard bus system are disconnected and locked
out.
Fuse and Contactor Check
1. Remove power circuit fuses and contactor from each
enclosure.
2. Remove control transformer primary fuses from each
contactor.
3. Use ohmmeter to verify continuity of fuses.
4. Check contactor and Hi-pot 16 kVAC or 23 kVDC
across each bottle for 1 minute. 5ma leakage is
failure.
Effective 11/97
Fig. 7 Thermal Capacity of a Typical Synchronous Motor
Start Winding
Bus System Check
With the contactors and power circuit fuses removed,
prepare the line-up for a megger test:
1. Close each isolating switch.
2. Disconnect metering taps, capacitors, arrestors and
any other equipment connected to the bus bar sys-
tem.
3. Then measure and record the megohm resistance
between phases of the bus bar system and between
each phase and ground. Track down and correct any
source of a low reading.
Page 9