The pressure metering pipe must be laid inclined in such a way that, for example, for measurements of fluids no
air pockets can form, and for measurements of gases no water pockets. If the necessary incline is not achieved,
then at suitable points water separators or air separators must be installed.
The pressure metering pipe must be kept as short as possible and laid without sharp bends, to avoid the
occurrence of irritating delays.
With liquid measurement media, the pressurized connection pipe must be degassed, since any gas bubble
inclusions result in measurement error.
If water is used as the measurement medium, the device must be frost-protected.
Safety notice: Only mount using the correct open-jawed wrench, and do not twist the device itself.
7.4 Starting up
The precondition for start-up is proper installation of all electrical feed lines and metering pipes. All connecting lines
must be laid such that no mechanical forces can act on the device.
Before start-up, the seal on the pressurized connection line must be checked.
7.4.1 Zero point adjustment
The pressure gauges are supplied calibrated ex works, so that as a rule there is no need for calibration works at the
installation point.
7.4.2 Venting
Liquid filled gauges should be vented for temperature compensation.
7.5 Subsequent relocation of the gauge (by the customer)
Recommendation: Do not remove the pressure gauge from one metering point and fit it in a different place,
as there is a risk of the measuring media being mixed, with unforeseeable chemical reactions.
8 Servicing
The device is maintenance-free. However, to ensure reliable operation and a long lifetime for the device, we
recommend that it is checked regularly.
8.1 Safety
When undertaking servicing work on the device, the pressure lines must be depressurized and the plant secured
against being switched on again.
8.2 Check on function, and recalibration
The check on function and recalibration is carried out at regular intervals, depending on the application. The precise
testing cycles should be adjusted in line with the operating conditions and ambient conditions. In the event of various
device components interacting, the operating instructions for all other devices should also be taken into account.
Check on display.
Check on function, in conjunction with downstream components.
Check of pressurized connection pipes for seal condition.