2.6 FIRST COMMISSIONING
After connecting the heater to the water supply, the hot water heating system, the electric
network, and after testing its safety valve (based on the valve manual attached), the heater
may be put into operation. Before opening the power supply, the tank must be filled with
water. The process of first heating must be executed by licensed professional who has to
check it. Both the hot water outlet pipe and safety armature parts may be hot.
During the heating process the pressurised connection water that increases its volume due
to heating must drip off the safety valve. In non-pressurised connection water drips off the
overflow combination faucet. When heating is finished, the set temperature and the actual
temperature of consumed water should be roughly equal. After connecting the heater to the
water main and electrical power system, and after checking the safety valve (following the
instructions attached to the valve), the heater can be put into operation.
Figure 6
- 14 -